Ljubljana Airport completes taxiway system upgrade

  • Get link
  • Facebook
  • X
  • Pinterest
  • Email
  • Whatsapp
  • Telegram
  • Reddit
  • Linkedin
  • Other Apps
NEWS FLASH


Ljubljana Jože Pučnik Airport today opened its new Taxiway J, marking the completion of a one-and-a-half-year upgrade of the airport’s taxiway system, which also included the overhaul of part of Taxiway A. Located 250 metres from the threshold of Runway 12, Taxiway J measures 170 metres in length and 30 metres in width, connecting the runway with the parallel Taxiway A. The new addition also provides extra space for the maintenance of airside surfaces and other airport infrastructure. The project involved asphalting nearly 9.000 square metres of new surfaces for Taxiway J and renewing close to 20.000 square metres of asphalt on the existing Taxiway A. The old asphalt removed from Taxiway A was recycled at an asphalt plant and repurposed at other locations. For illumination, approximately 35 kilometres of cabling and 59 new LED lights were installed on Taxiway J, integrated into a dedicated control system. In addition, ten new signs were erected to clearly mark the new taxiway.


Commenting on the project, Boštjan Šijanec, Director of Infrastructure at operator Fraport Slovenija, said, “The total investment in the construction of the new Taxiway J and the renovation of part of Taxiway A amounts to 5.35 million euros. This project represents a significant upgrade to Slovenia’s airport infrastructure and reinforces our position as the most modernly equipped airport in the region. With its successful completion, we have, in line with modern standards, provided an appropriate turning area for the largest aircraft at Runway 12’s threshold, marking an important step in enhancing the airport’s operational capabilities”.


August 12, 2025
Ljubljana Newsflash slovenia
  • Get link
  • Facebook
  • X
  • Pinterest
  • Email
  • Whatsapp
  • Telegram
  • Reddit
  • Linkedin
  • Other Apps

Comments

  1. Anonymous13:54

    they added TWY nobody needed, nobody asked for and they call it a major upgrade? Apron looks like plane graveyard, full of defunct aircraft

    ReplyDelete
    Replies
    1. Anonymous14:27

      That's true; airport needs to do something about that....year by year looks more like an aircraft graveyard

      Delete
      Replies
        Reply
    2. Anonymous15:19

      Why are some people so salty? The taxiway is needed for the future cargo apron on the north side of the airport.

      Delete
      Replies
        Reply
    3. Anonymous16:09

      First of all, not many aircraft are parked there nowadays maybe 2/3, even the one part at solinar platform is now almost clear (just 2 aircrafts).

      Second, even if they don’t have much traffic the taxi way was build solely if someone misses taxiway G and it happens many times if plane is too heavy, then they need to backtrack etc. if someone awaits on A for rwy 12, so stop being smart if you don’t know the background and what it looks like today.

      Delete
      Replies
        Reply
    4. Anonymous16:27

      Only in Balkans do people complain about an upgrade undertaken with private capital at the commercial airport

      Seriously, cheer up, every positive development is welcome

      Delete
      Replies
        Reply
    5. Anonymous16:47

      It's just the usual "wee I need Wyanair" guy.

      Delete
      Replies
        Reply
    6. Anonymous16:53

      We do need Ryanair, with what do you think most of us fly anyway? With Adria?

      I agree, it sounds more like something nobody needed or wanted.

      Delete
      Replies
        Reply
    7. Anonymous16:57

      I'm sorry but no one needs a specific airline. Flying is not a human right.

      And yes, Fraport will spend nearly 6 million € on something no one needs.

      Delete
      Replies
        Reply
    8. XYZ17:07

      Sorry but if they put 6 millions dollars to enhancing connectivity, that would be much better recieved...

      Delete
      Replies
        Reply
    9. Anonymous18:40

      Of course Ryanair passengers know which taxiways are needed on an airport and which aren't. My god the entitlement is real..

      Delete
      Replies
        Reply
    10. Anonymous21:29

      Anon 16.09, building 6 m € worth of taxiway just to enable straight in taxiing if high speed taxiway is missed, give me a break. In 30 years and some change in aviation, I've seen overun in LJLJ maybe ten times. High speed exit for RWY 12 is 1000% more needed. But yes. It's private company and it is obviously seen in that shithole of terminal (no wonder it reminds of Hofer/Aldi supermarket).

      Delete
      Replies
        Reply
    11. Anonymous21:51

      Take a chill pill, my dude.

      Delete
      Replies
        Reply
    12. Anonymous06:34

      So they invested millions to avoid something like 4 backtracks per year? It should be something more... Probably this was needed to comply with some regulatory requirements.

      Delete
      Replies
        Reply
    13. Reply
  2. Anonymous14:09

    Bravo Fraport!

    ReplyDelete
    Replies
      Reply
  3. Anonymous16:30

    LJU is known for its regular infrastructure upgrades.

    ReplyDelete
    Replies
    1. Anonymous16:54

      Yes, like the terminal which was way too late. It looked like the 60s when all of Eastern Europe (like Poland, CZ etc) had already upgraded them 20 years ago.

      Delete
      Replies
        Reply
    2. Reply
  4. Anonymous17:41

    Sorry for off topic... does anyone know if agean will continue maintaining its flights to Ljubljana next year? Flights are scheduled only till late march 2026. All other aegean destinations have already scheduled operations after march 2026.

    ReplyDelete
    Replies
    1. Anonymous19:52

      Surely if they'll fly in winter, the summer flights will follow suit

      Delete
      Replies
        Reply
    2. Anonymous06:33

      Aegean usually fully loads their summer schedule by the beginning of November.

      Delete
      Replies
        Reply
    3. Reply
  5. Anonymous20:03

    Is there any way I could somewhere see the bird view of the new taxiway? I have a hard time imagining how it looks and where it is.

    ReplyDelete
    Replies
    1. XYZ20:13

      Google maps

      Delete
      Replies
        Reply
    2. Reply
Add comment
Load more...

Post a Comment

EX-YU Aviation News does not tolerate insults, excessive swearing, racist, homophobic or any other chauvinist remarks or provocative posts with the intention of creating further arguments. A full list of comment guidelines can be found here. Thank you for your cooperation.

VINTAGE EX-YU


Loading cargo onto a JAT B727
1975

POPULAR THIS WEEK

Image

Wizz Air launching new Belgrade service, plans growth across EX-YU

Image

Croatia seeks more nonstop US flights

Image

Wizz Air makes further adjustments to Skopje and Belgrade network

Image

Wizz cuts London frequencies across EX-YU markets this winter

Image

The complete story of JAT’s iconic Boeing 737 fleet

Powered by Blogger
© EX-YU Aviation News 2008 - 2025